Commentary: Dulles Rail Phase II: A Common Sense Approach

This spring the Fairfax and Loudoun County Board of Supervisors will be required to make a final decision to opt in or out of Phase II of the Dulles Rail project. Rail through Tysons past the airport and into Loudoun is the largest public works project in the history of the Commonwealth and it has significant financial implications to the counties, its residents and businesses, and especially to the users of the Dulles Toll Road. As the Dulles corridor and Tysons are the economic engines of the region and the Commonwealth the project also has telling implications on our future job growth.

Dulles Rail enjoys overwhelming support among residents of both counties for its perceived transportation benefits. What many fail to realize is that Phase II falls short as a transportation project. For example Federal Transportation Administration administrator Peter Rogoff clearly told the Board of Supervisors the project fails to meet even President Obama's liberalized cost benefit standards for new transit projects. This is why the federal government is not able to contribute to the cost of Phase II.

The project will only increase the transit ridership mode split in the corridor by approximately 3 percent-5 percent in 2025.

Because there are no express routes and over 14 stops, the trip from Dulles Airport to the Potomac River on a completed Silver Line is projected to take over one hour (average speed less than 25 MPH) — longer if they fail to figure out the current congestion at the Rosslyn crossing. There is no time advantage over the car or express bus.

According to the project's projections, the Dulles airport station will only generate about 10 percent of the traffic on the Silver line, the majority being airport employees, not travelers, and handle less than 15 percent of the airport's total traffic.

That said, the project has the potential to be a huge economic boom to the corridor and Fairfax County; at least it did until the cost went up along with the projected tolls on the Dulles Toll Road that will finance 75 percent of the project. The new projections of the tolls necessary to finance the debt have not been released. Even with federal TIFIA financing that pushes the first debt payments out 10 years, it is a good bet that the tolls will exceed $8 each way by 2020 excluding the Greenway.

The same overwhelming majority of people that favor Dulles Rail Phase II also say that they would not live, work or start a business in a corridor where there are $8 tolls. What will the tolls do to the economic engine of the County and the Commonwealth? Will they do more harm than the benefit of rail? These are questions that I have repeatedly tried to get the Fairfax County Board to study and address without success.

We lost a chance to further improve the project when we approved the Memorandum of Agreement (MOA) on Dec. 6. Unfortunately our next vote will be under a tight timeline - 90 days after we get the engineering numbers and the projections for tolls - and it will be an up or down vote. It is imperative that we use the time between now and the vote to do everything in our power to improve the project and its finances and to have all of the information we need to make an informed decision available. We need to ask the tough questions, negotiate hard and put ourselves in the best position possible to make the most critical decision the Board of Supervisors will make this term.

The following are the common sense steps that I believe we should take now in order to ensure that we are in the position to negotiate the best deal we can for the citizens of Fairfax County and make the right decision in the spring. Unfortunately time is short and most of these actions are not currently being taken.

Immediately begin a study of the economic impact of the tolls on the Dulles corridor and Tysons. It is critical that we understand the impact that the high tolls will have on the economic engine of Fairfax County and the Commonwealth. Will the high tolls strangle the corridor and chase businesses and residents away? I do not have the answer but my discussions with residents and business leaders give me great pause. On April 26 2011, I proposed such a study but it was rejected on a party line vote. We should not be afraid to have this answer in front of us before we vote - in fact it is critical that we do have it.

Explore and begin negotiation on additional funding sources. At the Dec. 6 meeting I proposed that we have the County Executive begin looking at additional revenue sources including the sale of air rights over the toll road at the stations, development rights at the airport station and/or a modest toll on the access road as ways to relieve the burden on the toll road users. While air rights may not be practical in today's environment they could be negotiated now to relieve the debt payments in 10 years. I believe there are other potential funding sources - including a potential private partner that would help fund the project.

Work to immediately improve the MWAA Board. In 2005, then Governor Kaine gave the Dulles Toll Road and the Dulles Rail project to MWAA - an interstate body with no elected representatives and a majority of appointees that live outside of Virginia. This was done without the approval or consent of the General Assembly or local governments. By all accounts the relationship between the partners and MWAA is not good at best. In order to work the best deal possible for both the airport and the county we need to have a partner that is open to talk.

Congressman Wolf worked a solution to improve Virginia's representation through Congress. It was signed into law by President Obama and adds two Virginia, one D.C. and one Maryland representative to the MWAA Board. Unfortunately MWAA refused to seat the new members until the compact changes have been ratified. Senator Colgan has introduced emergency legislation (SB 237) to ratify and seat the two new Virginia members immediately. Emergency legislation requires 80 percent approval and the bill has bi-partisan support - even that of Del. Ken Plum, a Dulles Rail supporter for many years who believes it is the right thing to do.

Unfortunately, despite the bi-partisan and business community support, the Board voted twice (most recently on Jan. 23) on a party line basis against supporting these efforts to improve the MWAA Board on the basis that it wasn't in the best interest of "regionalism." As the Washington Post pointed out (Jan. 26) "a prolonged period of confusion could delay the Silver Line's progress, possibly by casting doubts on the viability of contracts." We need to fix the MWAA Board immediately.

Clarify No Mandatory Project Labor Agreement (PLA). Not only did former Governor Kaine transfer the project and the toll road to MWAA, he added insult to injury by appointing the Vice President of LIUNA, a Maryland-based union that represents and is paid by the union workers on Phase I (and potentially Phase II), to represent Virginia on the MWAA Board. Since then he has been working behind the scenes to make sure that Phase II contains a Project Labor Agreement (PLA). The Fairfax County Board had a chance to clarify that there would be no mandatory PLA when the MOA was being negotiated and they opted not to. Now Delegate Comstock has submitted legislation that would prohibit a mandatory PLA (but not prevent a voluntary one as in Phase I) and despite broad support from across northern Virginia, the Fairfax County Board has yet to endorse it. Governor McDonnell has made it clear that he will not support exporting the jobs outside of Virginia - 96 percent of Virginia's workers are non union. We need to clarify that there will be no mandatory project labor agreement or we risk exporting these jobs outside Virginia and eliminate any financial contribution from the state - be it $150M or $500M.

Continue working to drive down the project's cost. The negotiations around the MOA approved in December resulted primarily in shifting cost from the Phase II project to the other jurisdictions - parking garages to Loudoun and parking garages and the Route 28 station to Fairfax County — not real cost reduction. Relocating the airport station resulted in the only true material cost savings. I understand that efforts are underway to engineer additional cost savings and these discussions need to continue. I believe we should also reach out to the American Society of Civil Engineers, located in Reston, to see if they have any suggestions or recommendations.

Understand the impact of Loudoun's decision. We need to clearly understand the impact on the project (do the stations still get built), the finances of the project (who picks up their share), and the operating expenses if Loudoun opts out of the project. The Loudoun Board has seven new members and many are questioning the cost and benefit of Phase II. According to Chairman Scott York, Loudoun County's participation in the project is unclear at this point.

Understand the impact of the ongoing operating expenses of Phase II. On Jan. 23 the Board approved my request for a 15-year projection of operating expenses that Fairfax County taxpayers will be on the hook to pay as a result of operating deficits. The operating deficit is shared among jurisdictions based on a complicated formula that includes the number of stations. I also asked for other potential capital costs for ongoing maintenance and expansion.

Develop and understand the scenarios if we were to opt out of the project. I fully expect the Fairfax County Board to vote to stay in the project but the Board and the public should understand what happens if Fairfax County were to opt out of the project. Does the line get built anyway without the stations or does the project die? What are the other options? Montgomery County recently looked at their options for the I-270 corridor and chose a Bus Rapid Transit (BRT) system over a rail system because of the cost, speed in completing, flexibility, and the ability to run express trips. Loudoun County is working on understanding its options and we should as well.

Determine if the private sector can fund the Route 28 station without County investment. Supervisor Frey has repeatedly asked about the ability of the private sector to build the Route 28 station. We also need to understand the opportunity cost of them building the station — what doesn't get done in terms of other transportation infrastructure if they do build the station.

Determine how we will fund the project shortfall and any overruns. We have a shortfall of over $100 million already identified on the project. We have not yet identified the source of funds to cover the shortfall — with all of the transportation needs in Tysons and throughout the County. I believe it is critical to be transparent on how we intend to pay for the shortfall, the operating expense deficits and any project overruns.

Get new projections on ridership and assess the impact of the changes. The latest ridership forecasts were made as part of the Environmental Impact Statement in 2002. A lot has changed in Loudoun and Fairfax since then. We need to know the latest numbers and their impact on the project and its finances.

Get input from the public. Thanks to the repeated efforts of Supervisor Cook, the Board has agreed to hold a public hearing before the Board of Supervisor's vote on the project. I believe it is important that we hear from the public on this critical project.

These common sense steps should be taken now in order to ensure that we are in the position to negotiate the best deal we can for the citizens of Fairfax County and that we have the information we need to make an informed decision on Phase II so Tysons and the Dulles Corridor can continue to prosper as it has over the last 20 years.

Please give me your thoughts on Phase II. Whether you live in Springfield, Clifton or McLean, this project will impact you because it impacts the economic engine of Fairfax County and the Commonwealth.

Pat Herrity is the Springfield Supervisor on the Fairfax County Board of Supervisors.

Comments

Bob_Bruhns 3 months ago

At least several costs in Dulles Rail Phase II are about twice what would be expected, based on recent similar work in similar areas.

FRANCONIA-SPRINGFIELD

Dulles Rail Phase II is about five times the size of the Franconia-Springfield Metro job, but it costs 17 times as much.

Franconia-Springfield: 3.3 miles of track and a station - $175 million in 1997.

Dulles Rail Phase II: 11.6 miles of track and six stations - over $3 billion in 2012.

Was there 3.5 to 1 inflation since 1997? No.

FAIRFIELD, CONNECTICUT METRO STATION

A metro station in posh Fairfield, Connecticut cost $43.7 million, while our comparable Rt 28 station will supposedly cost $83 million.

http://www.ctpost.com/?news/article/?Millions-more-needed-to-fin?ish-Fairfield-Metro-144323?5.php

http://www.mta.info/mnr/?html/fairfield_metro.htm

http://www.bruhns.us/civic/DullesRail/2011-08-03-Fairfax-County-RT28-Station-Cost-Confirmation.pdf

DULLES RAIL PHASE II PARKING GARAGES

http://www.washingtonpost.com/wp-srv/metro/documents/Dulles_Rail_White_Paper.pdf


Herndon-Monroe: $51.4M, 1949 spaces ($26,372 per space) Rt 28: $53.5M, 2027 spaces ($26,392 per space) Rt 606: $51.9M, 1965 spaces ($26,412 per space) Rt 772 North: $37.8M, 1434 spaces ($26,359 per space) Rt 778 South: $40.6M, 1540 spaces ($26,363 per space)

TOTAL: $235.3M, 8915 spaces ($26,394 per space)

In comparison, here is a recent price analysis on parking garage costs in North America.

http://www.vtpi.org/tca/tca0504.pdf

$26,394 per space is VERY much on the high side. Our cost should be more like the US average of $15,000 per space.

CONCLUSION

We are clearly being handed a $40 million overcharge for the Rt 28 station. What about the other five stations? Should we not expect that they will cost $40 million too much, as well?

And it looks as though we are being overcharged by at least $101.6 million for the parking garages too.

So we have a definite $141 million overcharge that can easily be seen in these two items alone, and probably another $200 million overcharge from the other five stations in Dulles Rail Phase II. I think it is very likely that the total does indeed equal or even exceed $340 million of overcharge for the stations and parking garages alone!

THESE ARE NOT SMALL ERRORS - THESE ARE NEARLY TWO-TO-ONE EXCESSES! What is going on here? And what else will I find as I examine the rest of the line items?

If MWAA and FTA managed to overcharge us so much for THOSE things, maybe it's time to ask what ELSE they did. I think it is time for a serious and official review and adjustment of the costs that MWAA and FTA are trying to force upon this region. Not another FTA whitewash, but a real review and adjustment. No?

0

jeff4va 2 months, 3 weeks ago

PLAs Add Value

Opponents of Dulles Rail are conveying a false message. They imply that everyone working on Dulles Rail must belong to a union. This is untrue. For Dulles Rail, no one will be required, directly or indirectly, to join a union.

A Project Labor Agreement will require a firm schedule and no change orders.

Because overruns and change orders are part of every contractor’s business model, contractors do not like Project Labor Agreements. This is why they are spreading misleading information.

PLAs lock-in schedules and costs. A PLA for Phase II of Dulles Rail will benefit every taxpayer in Fairfax and Loudoun counties.

PLAs also protect skilled workers. Contractors can’t low-ball their employees. PLAs require that all skilled workers get the prevailing wage plus minimum training. The wage floor is very low. For the average skilled worker on Phase I of Dulles Rail, the floor is $20 an hour. That is only $40,000 a year; so low that it qualifies a family for free school lunches.

When someone like Mr. Herrity tells you that PLAs are bad for taxpayers, or that PLAs mandate unions, ask to see the evidence. You won’t find it.